Understanding minimum order quantities, factory production cycles, and shipping lead times for Korean packaging programs.

Packaging Production Schedule Timeline
Manufacturing supply chain timeline milestones from tooling to export pallet dispatch.

Planning realistic production schedules and order quantities ensures smooth product launch execution.

Manufacturing Timelines & Quantities

  • Stock Components — 1,000 to 3,000 units | Lead time: 7 - 14 business days
  • Custom Color Molding — 5,000 to 10,000 units | Lead time: 21 - 30 business days
  • Custom Surface Decoration — 5,000 to 10,000 units | Lead time: 25 - 35 business days
  • New Mold Fabrication — 10,000+ units | Tooling lead time: 35 - 50 days + sampling

Factors Influencing Production Cycles

Custom color masterbatch approval, multi-color registration passes, and peak seasonal factory schedules (such as Q4 launch rushes) directly affect final dispatch dates.